GST BOCES Capital Project Update

The Greater Southern Tier BOCES was previously approved for building projects on two of its campuses. These improvements will involve creating large gymnasiums/ multi-purpose spaces for regional use on the Wildwood (Hornell) and Coopers campuses. We are thrilled to see the progress! 

The gymnasium project at our Wildwood Campus began in September. The foundation work and steel framework are complete. Masonry work is taking place and roofing is scheduled to begin in early February. Additionally at Wildwood, underground utilities are underway, including sewer, water, gas, fiber optic and electric. 

Coopers Campus gymnasium work began in October. The foundation and steel framework are complete. Masonry and underground utility work are scheduled to begin next week. 



#PROUDTOBEGST